Steel building under construction at Sekolah Menengah Islam Hidayah, Johor Bahru. See the function of roof truss in this building.

Preparing the ground to be concreted to provide raft foundation for the structure

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

After reinforcement (using BRC) was put in position, the concrete was the poured and leveled. This process is to provide a layer of ground slab or better known in this case as raft foundation.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

The concrete raft foundation was then left for few days to allow for curing. At the same time the workers are busy preparing the trusses for roofing and containers for the building.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Containers are being lifted and positioned in place as planed.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Positioning process. Containers are lifted and positioned according to the plan.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Condition of the building under constriction. There is no column being used. Roof structures are totally rest on the stack of three layers containers.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Fabrication stage of the trusses

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Fabrication stage of the trusses. Painting the trusses.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Full set of a truss is ready to be fully painted. The green in colour is undercoating paint.The final colour of paint to be black in color.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

Trusses are then lifted to the position using 50 ton mobile crane one by one.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

This building is under construction. It is a structural steel building. Shown here is the photo of the roof trusses for the building.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru

The metal deck roofing is almost done. Gaps in between are allocated for transparent roofing purposely planned for daylight lighting, reducing the use of electricity.

Asrama Banat (Perempuan)

Sekolah Menengah islam Hidayah, Johor Bahru